From the first pre-construction meeting to the ceremonial delivery of your front door key, we keep you informed every step of the way. After all, we’re not constructing a new house, we’re building your new home. There’s nothing more important to us than that.

Good communication helps us serve you better and keeps you informed. Please feel free to contact your AllenStyle representative anytime you have a question, concern, or need more information. We’ve also created a handy online tool called Builders Trend. It’s a very convenient way of “checking the job” without actually having to go to the site.

SAFETY DURING CONSTRUCTION

SAFETY POLICY DURING CONSTRUCTION

Your safety is of upmost importance to us. Please contact us any time you wish to schedule a site visit. Our insurance carrier requires everyone wear a hard hat for protection. They also require a member of our staff accompany guests during a scheduled visit. Please remember:

RULE ONE IS SAFETY FIRST.

LOCKS & KEYS

When exterior doors and locks are installed, a master key will be needed to access the home. If you wish to enter your home during the construction process, please contact your AllenStyle Homes representative to schedule a site visit.

CONSTRUCTION TIMELINE

WEEK 1

Email Architect, Superintendent, Design Coordinator. Turn contract into office. Preliminary drawings emailed.

WEEK 2

Pre Construction Meeting with Sales, Superintendent and client. Goal sign off on plans.

Answer any questions, regarding construction.

Set expectations.

Explain building process.

Communication System.

Set first appointment with design coordinator.

WEEK 3

Pre Construction Meeting with Sales, Superintendent and client. Goal sign off on plans.

Answer any questions, regarding construction.

Set expectations.

Explain building process.

Communication System.

Set first appointment with design coordinator.

WEEK 4

Architect receive foundation drawings from engineers.

Architect receive plans from print shop.

Architect receive permits.

Dirt begins to move (lot grade).

Superintendent set form for foundation.

Select kitchen backsplash and bathroom accents.

Select granite for all countertops.

WEEK 5

Ground Plumbing begins.

Plumbing ground inspections by Municipality.

Foundation sanded for city inspection.

Select carpet for Master bedroom, guest bedrooms, office/bonus room.

Discuss Lighting at selections appointment.

WEEK 6-7

Foundation Inspection.

Pour concrete slab.

No exterior color changes past this point.

Framing Begins (takes two weeks/pending weather).

WEEK 8-9

Windows and exterior doors installed.

Start rough-ins (piping behind the walls and above ceiling, wiring, ducts, ect.).

Brick starts.

Lighting and hardware sections finalized.

No concrete changes.

Rough-ins inspection.

No electrical or other wiring changes past this point.

WEEK 10

Start sheet-rocking and texture.

Insulation installed.

Cabinets and trim installed.

Driveway, sidewalks and porches poured.

No paint/stain changes.

No granite changes.

No tile flooring, appliances or faucet changes.

WEEK 11

Exterior and interior paint and stain.

WEEK 12

Countertops installed.

WEEK 13

Tiling.

Get with lender, sign documents, provide W-2, taxes and paystubs and line up insurance.

Final installations (plumb, electrical, HVAC and low voltage).

WEEK 14

Final inspections.

Wood flooring installed.

Carpet installed.

House final cleaning.